Steinau-Hintersteinau

  • Start of construction January 2017, start of operation February 2018
  • 8 WEA, type VESTAS V126-3.45 MW, hub height 149m

The wind farm 36396 Steinau-Hintersteinau has been planned by RENERTEC since 2014. After receiving the building permit in December 2016, construction work began in January 2017. The plants will be commissioned in February 2018.

The grid connection is made via the company's own substation to the 110 kV grid of Avacon AG.

As usual RENERTEC is providing the technical plant management for the whole wind park.