Feldatal – Am Biehnes II

  • Planning commenced in 2011 and the wind park was initiated in 2015
  • 2 Enercon E 115 wind turbines (height of tower 149m), each with a performance of 3.0MW
  • Extension of RENERTEC's wind park Mücke-Feldatal-Ulrichstein built in 2012 (14 Enercon E82 wind turbines (hub height 108m), each with a performance of 2,3MW)
  • Feed in into an own substation, which was erected for the existing wind park Mücke-Feldatal-Ulrichstein by RENERTEC in 2012

The wind park Feldatal - Am Biehnes II was planned and erected by the RENERTEC.

RENERTEC provides the technical plant management for the 16 windmills and the substation.